Retaining Wall Construction

Retaining Wall Construction

Retaining Wall Construction – There are many ways and methods of building a retaining wall. It all depends on the retaining wall type.

The example below is for the construction of a reinforced block retaining wall. The design is based on cantilever principles. The wall is connected to the foundation and looks like an L shape. The retained earth sitting on the foundation helps the retaining wall design properties.

The alternative to this design is a gravity retaining wall, but this uses more blocks.

Retaining Wall Construction Design

Before you can build the retaining wall, it needs to be designed. Normally some ground investigation data is required for the retained earth and the ground bearing pressure. This can be done by excavating trial excavations and giving the information to a structural engineer who will design the wall.

The design of the wall will look similar to this design drawing. You can look at our reinforced block design guild table for more information.

Step 1 – Excavation

Excavate the surrounding area in preparation for the retaining wall. Ensure the formation ground is firm. Lay 50 to 100mm of blinding concrete over the formation to give a flat and level surface. This also protects the formation and stops any contamination of the reinforcement.

Step 2 – Formwork

Place formwork for the raft. Ensure there is 40mm of cover for the reinforcement. The reinforcement type and size will depend on the size of the structure and the design.

Step 3 – Reinforcement

Fix the starter bars in position. It is important that they are placed accurately. To do this fix supporting timbers from the edge formwork as shown. Depending on the size of the block the centres will be either 600mm or 800mm. The dimension from the face of the wall to the bar location is 450mm for 600mm blocks and 650mm for 800mm blocks.

Step 4 – Concrete

Pour concrete into the formwork. Make sure the started bars are not moved. It is worth checking to starter bars before the concrete sets.

Level the concrete to the top of the formwork and leave with a light tamp finish.

The strength of the concrete will be given by the design but is normally a C40 mix.

Step 5 – Constructing The First Layer

Lay the first layer of blocks. Place them over the started bars. On completion of the first layer, lay the back drainage pipe. It is important that any water behind the wall is taken away to stop hydrostatic pressure building up.

This is done by laying a perforated pipe and backing filling with clean stone to act as a filter. The clean stone fill can be wrapped in geotextile to filter out any fine particles from the soil that will eventually block the stone filter.

Step 6 – Compete The Construction

Build the wall to full height and backfill with clean stone and retained earth as you go.

Fit the vertical rebar to the design and grout in using a non-shrinkable grout. This is important for the structural stability of the completed wall and to stop the rebar from corrosion.

Retaining Wall Detail Design

Retaining Wall Construction Video

Call Back or Ask a Question on Retaining Wall Construction

Complete the form below to ask a question or request support. I normally answer questions and respond to requests as soon I notice the message.

Alternatively text or call me on 07896 246 224 complete the form on the contact us page or BOOK a CALL

© 2018 Retaining Wall Solutions – Made with passion!